LNG vs pumped hydro: will NZ choose to import risk or build cleaner resilience?

As the escalating US-Israel war on Iran drives a global fuel supply crisis, New Zealand is eyeing two major – and very different – projects aimed at bolstering its long-term energy security.

While one risks deepening the country’s reliance on the very fossil fuel systems now in turmoil, the other offers a more sustainable alternative.

In February, the government announced plans to develop a liquid natural gas (LNG) import terminal, likely in Taranaki, under its fast-track process.

This would replace New Zealand’s dwindling natural gas supplies, act as a backstop for dry-year electricity shortages and help stabilise power prices.

But it has been reported that ministers may now be reconsidering the project, as surging global gas prices due to the Middle East conflict undermine its economic case.

Meanwhile, the government last week referred another major energy project to its fast-track consenting panel: a pumped hydro scheme at Central Otago’s Lake Onslow.

Once a government-led initiative, the project is now being steered by a private consortium chaired by former Meridian Energy chief executive and Transpower chairperson Keith Turner.

It would store excess water in a high storage lake when it is plentiful and release it to generate electricity when the hydro lakes are dry, acting as a “battery” to shore up intermittent renewable electricity.

As New Zealand seeks to establish a resilient energy system for the decades ahead, while meeting its climate change commitments, the contrast between these two schemes is hard to ignore.

The follies of fossil fuels

The latest oil shock is forcing countries to confront the fragility of global fuel supply chains – and the risks of relying on them.

Building renewable energy is increasingly being viewed as a path to energy independence. After Russia’s 2022 invasion of Ukraine disrupted gas supplies, Europe accelerated its shift away from imported gas, and the current rising global fuel costs are rapidly increasing the uptake of electric vehicles.

At the same time, the urgency of cutting fossil fuel use has become existentially important, as rising global temperatures drive more frequent storms, floods, wildfires and sea-level rise.

Only 4% of New Zealand’s emissions come from its largely renewable electricity system, while 34% come from transport and industrial heat. Electrifying these sectors would cut both emissions and reliance on imported fuels, helping align with the Paris Agreement’s goal of limiting global warming to 1.5°C above pre-industrial levels.

But electrification will increase demand for renewable electricity. And because wind and solar are variable, the system still needs backup when renewable generation is too low.

Two projects, two paths

Under the government’s terminal proposal, LNG would be imported to shore up dwindling gas supplies, with domestic production having declined over the past decade.

But the proposal cuts against both climate and cost goals. Although gas is meant to produce lower emissions than coal, transporting it around the world can result in higher total greenhouse gas emissions than coal, while leaving New Zealand exposed to volatile international markets.

That concern was echoed in a government-commissioned report by Frontier Economics, which found LNG imports for dry-year risk made “no economic sense”.

LNG is a costly way to generate electricity: around NZ$200–$250 per megawatt-hour (MWh) of power produced, without the cost of the terminal. By comparison, the fully loaded cost of domestic gas-fired power is roughly $125/MWh.

The terminal itself is expected to cost more than $1 billion, with those costs likely passed on to consumers through a levy. Subsidising the terminal risks undermining the commercial viability of cheaper renewable options.

In addition to this, opening an expensive LNG “portal” could incentivise new gas-reliant industries, locking in demand for this imported fossil fuel for decades.

By contrast, pumped hydro is a renewable alternative for shoring up intermittent electricity supply.

In a very dry winter, New Zealand can be short of around 5 terawatt-hours (TWh) of water for electricity generation – or about 12% of total annual demand.

The proposed Lake Onslow project would likely store 4TWh of water for generation. But is also not without its drawbacks. One is that it would raise the existing lake by around 20 to 50 metres.

This would have impacts on wetlands and native fish species, and environmental groups have noted the trade-off between local environmental effects and the wider climate benefits.

Bridging the gap

The Onslow scheme will take at least four years to build. But in the meantime, New Zealand has other firming options available to help bridge the gap.

Geothermal generation could be maximised, the Huntly power station can run on wood pellets, and coal and diesel generation could be retained as temporary backup during dry or high demand periods.

The main hydro lakes could also be given slightly more range, and electrified coal boilers could be retained for occasional use.

Demand response – where electricity use is reduced or shifted at peak times – is already being used in New Zealand. But this could be expanded, with large industries cutting output or households reducing demand, such as turning off hot water heating during the brief evening peaks.

Access to vehicle-to-grid battery systems could also be accelerated with government support.

If the crises facing our climate and fuel supplies point to a single message, it’s that energy resilience lies in reducing dependence on imported fossil fuels.

New Zealand has an opportunity to do so by incentivising electrification, facilitating temporary electricity firming, halting plans for the LNG terminal and pushing ahead with the Lake Onslow proposal.

Read more https://theconversation.com/lng-vs-pumped-hydro-will-nz-choose-to-import-risk-or-build-cleaner-resilience-279552

Split Corrugated Conduit for Flexible Cable Protection

For wiring assemblies in vehicles, machinery and equipment, choosing suitable cable protection helps keep cables organised and reduces direct contact with surrounding parts. Mojak Plastics supplies plastic tubing and conduit options for different installation needs, and split corrugated conduit can... Read more

Trailers Melbourne Buyers Can Compare: When Box Trailers Make Sense

For many homeowners, businesses and tradespeople, trailers Melbourne customers use every week need to be versatile enough for changing loads. A box trailer can be particularly useful because its enclosed sides help contain cargo while providing a straightforward loading area... Read more

Bottle Label Printing That Balances Design and Readability

Product labels need to attract attention while making information easy to find and understand. On a bottle, the available space may be limited by the container’s shape, so every design decision matters. Bottle label printing should account for visual hierarchy... Read more

Office Cleaning Melbourne: Planning a Consistent Workplace Routine

Businesses looking for office cleaning Melbourne need a plan that reflects the way their workplace operates. A clean office supports day-to-day organisation, helps shared spaces remain presentable and gives employees and visitors a more orderly environment. Eco Green Cleaning Management... Read more

Pinboard Solutions for Offices, Schools and Shared Information Spaces

Why a Pinboard Remains Useful A pinboard provides a simple way to display information that needs to remain visible without being rewritten. Lawdex supplies fabric and cork options for offices, schools, staff areas and other environments. A pinboard can be used... Read more

Retractable Hose Reel: A Practical Guide To Choosing The Right Hose Storage

A retractable hose reel can make hose storage more organised, accessible and practical in workshops, commercial facilities, service areas and other working environments. Instead of leaving a hose coiled across the floor or requiring staff to manually wind it after... Read more